Earnings Calls

Last Earnings Call

Fiscal Period
Q4 2026
Call Date
Sep 9, 2026
AI Summary
Q4 2026

Execution: Contango said it completed its major field programs on schedule and within budget, including nearly 70,000 meters of drilling, road construction, underground development, and tunneling across its projects.

Manh Choh: The oxygen plant for the higher-grade, sulfide-rich South Pit is operating as planned; recoveries are expected in the 80s to low 90s, with production expected to rise and costs to fall as pre-stripping is completed.

Production outlook: Management is guiding toward 75,000 ounces of production next year at an all-in sustaining cost of $1,200-$1,300 per ounce, using a $3,700 gold price for financial projections.

Lucky Shot: The newly discovered KM vein returned grades of up to 10 ounces per tonne, and a 1,100-meter underground drill program is expected to begin shortly, with results planned before year-end.

Kitsault: More than 50,000 meters were drilled this season, above the original 40,000-meter plan. An updated resource estimate is expected within weeks, with a focus on converting inferred resources into indicated resources.

Johnson Tract: The access road, bridges, laydown area, and portal pad are substantially complete, setting up tunnel construction and year-round underground work next year.

Funding: Management said exploration and development programs have been funded from Manh Choh cash flow without returning to the capital markets, and expects current net debt of approximately $47 million to be eliminated by the end of next year.

Key Financials
Total drilling
Nearly 70,000 meters
Kitsault drilling
More than 50,000 meters
Kitsault historical resource
Almost 65 million ounces of silver
Lucky Shot KM vein drill program
1,100 meters
Manh Choh recoveries
80s to low 90s
Manh Choh production
75,000 ounces
Manh Choh all-in sustaining cost
$1,200-$1,300 per ounce
Gold price assumption
$3,700 per ounce
Net debt
Approximately $47 million
Potential operating cash flow
Well in excess of $200 million, probably almost $250 million
Kitsault resource estimate timing
Within a couple of weeks
Johnson Tract road and barge facility construction timing
May 2028