First Time Loading...
A

AngloGold Ashanti Ltd
JSE:ANG

Watchlist Manager
AngloGold Ashanti Ltd
JSE:ANG
Watchlist
Price: 43 920 Zac 1.81% Market Closed
Updated: May 13, 2024

Earnings Call Transcript

Earnings Call Transcript
2020-Q1

from 0
Operator

Good day, ladies and gentlemen, and welcome to AngloGold Ashanti’s First Quarter 2020 Market Update. All participants will be in listen-only mode. There will be an opportunity to ask questions when promoted. [Operator Instructions] Please note that this conference is being recorded.

I would now like to hand the conference over to Mr. Stewart Bailey. Please go ahead, sir.

Stewart Bailey

Thanks, Judith, and thanks, everybody, for joining us for our Q1 2020 conference call, which is a first for us being done remotely with all of the speakers in different locations. You will also note on the second Slide in the presentation our Safe Harbor statement, which covers forward-looking statements, have a lot of important information in there, and I’d urge you to look at it.

I’m going to hand right over to Kelvin. And then after that, we have Christine, Sicelo, Ludwig and Graham talking to their respective areas of the business. Kelvin, please go ahead.

K
Kelvin Dushnisky
Chief Executive Officer

Well, thank you, Stewart, and thanks, everybody, for joining us for the Q1 update. Our overall objective is to safely deliver better quality production aimed at widening margins, extending mine lives and improving the portfolio. The current health crisis does not change that.

We’re committed to maintaining discipline in the current gold price environment, with emphasis on further deleveraging the balance sheet, progressing the ongoing divestment processes, enhancing margins, growing oil reserves, and ramping up Obuasi to commercial production.

And importantly, we work to maintain and strengthen our license to operate through effective ESG practices, as demonstrated in our ability to mobilize quickly and effectively to support the global fight against COVID-19.

On the safety front, regrettably, there were four fatalities in Q1, which occurred in two separate fatal incidents in March at the Mponeng mine. The first incident occurred on 5 March, where three of our colleagues were fatally injured in a seismic-related incident, caused by a large fall of ground roughly 3.6 kilometers below surface.

The second took place on March 16 in an accident during an underground horizontal transport incident. And subsequent to the quarter-end, an employee of Covalent Water passed away as a result of injuries sustained in an electricity-related incident suffered earlier in the year.

These fatalities were very difficult for us. We went almost two years without a fatality across the portfolio, and it’s a hard reminder of the essential work and attention required to achieve zero harm at our operations. We’ll intensify our efforts to eliminate injuries from the workplace.

We delivered a strong performance across a number of fronts during the quarter: production was solid; our operations generated exceptionally strong cash flows even as we invested $90 million in growth capital, principally in the Obuasi redevelopment; our drilling program to extend mine life and improve flexibility moved a head according to the plan; and we announced the deal to sell our South African assets, in line with our strategy of streamlining the portfolio and better focusing capital allocation.

The business is in very good shape. Production was 716,000 ounces, with strong performances from Kibali, Geita and Iduapriem. COVID-19-related stoppages impacted production by 11,000 ounces towards the end of the quarter. All-in sustaining costs rose 4% year-on-year, or $38 an ounce, about half of which was related to COVID-19 impacts.

Cash flow was robust, demonstrating significant leverage to the rising gold price. Especially pleasing was the increase in free cash flow before growth capital, the metric on which dividends are calculated, which was up 231% to $94 million. The strong cash flow performance would have been even stronger were it not for some working capital lockups, and Christine will talk to that in a few minutes.

Net debt continues to fall and was down 10% year-on-year to $1.6 billion. Gearing also continues to get better, with net debt-to-EBITDA at 0.5 times, well below our one time target through the cycle.

We continue to see margins expand, helped by the higher gold price. Our all-in sustaining cost margin grew to a healthy 34%, compared to 28% on average last year. There’s room for that to widen further, particularly given where spot prices are.

From a capital allocation standpoint, our strategy and clear approach to managing capital remains unchanged and continues to serve the company well, including as we manage through the pandemic.

As we flagged previously, converting our earnings into cash has been a challenge in some areas. At Kibali and the DRC, Barrick is working hard to progress cash repatriation. In Ghana and South Africa, we’re working to reduce care and maintenance costs.

In 2019, we announced sales processes for several of our assets aimed at streamlining the portfolio. You’ll have seen our decision to retain our CVSA operation in Argentina. This, after running a comprehensive process with various offers at surface, but none that reflected, but we consider to be full value for this asset.

We believe that the maximum value from CVSA will be better realized inside the AngloGold Ashanti portfolio. We’re now exploring opportunities across the lease area to unlock further reserves and extend the mine life. The South Africa portfolio sale remains firmly in process, and you will have seen Harmony’s plans to finance the transaction announced last week.

Competition Commission approval has been achieved ahead of our internal schedule. And now we’re awaiting Section level – Sections 11 approval from the DMRE as the last key regulatory step. The Sadiola sale is also moving ahead with some delays resulting as we navigate through COVID-19-related logistics, but nothing material, and we still anticipate closing the transaction this quarter.

Finally, we’re very pleased with our partnership with B2Gold, who are managing the Gramalote JV very well, including during these COVID-19 circumstances. We’re committed to doing our part to stop the spread of COVID-19. We’re focusing on ensuring we adapt quickly to the changing environment, and that interventions are implemented as effectively as possible at each site. A critical part of this is working with governments and a range of other stakeholders in flattening the curve.

We’re doing this while ensuring their mines operate safely, each of which make an important contribution to the economies of the countries where we operate. We’ve introduced a number of initiatives on our sites and the surrounding communities to help stop the spread of the virus.

I’m doing this, we’ve applied a lot of lessons learned in fighting other illnesses over time, including the 2014 Ebola outbreak in West Africa and the ongoing fight against TB and HIV in South Africa, where we’ve achieved some notable success.

At a country and state level, we’ve contributed in a number of ways from donating hospitals, as well as running extensive personal hygiene and education campaigns. At the community-level, we provided hand washing stations in areas with low access to reticulated water, and we provided alcohol-based sanitizers to healthcare facilities, both large and small.

At a site level, we have the full suite of mitigation steps in place. These are all in line with best practice and developed in close consultation with national and local health authorities.

Our liquidity runway has been bolstered by drawing down the full $1.4 billion available under the multi-currency RCF and securing a new $1 billion standby facility to help weather any unforeseen events that the pandemic may bring. That gives us a very healthy $2.3 billion of available liquidity.

Inventories of critical spares are now at an average of four months across the portfolio, which is within our three to six-month target range, depending on the needs and specific risk profile of each asset. We’re also building ore stockpiles to provide additional operating flexibility where needed. And we work closely with our associated partners at the Rand Refinery in Johannesburg to ensure continuity of inbound transport of gold doré from our African operations through accredited private charters.

Due to the uncertainty that remains over severity and duration, as well as the consequences of the different measures taken by governments around the world to safeguard public health, the decision was made on March 27 to withdraw guidance for 2020. That said, internally, we continue to work toward achieving our objectives set earlier in the year.

We saw temporary stoppages during March and April at our South African assets, Cerro Vanguardia and Serra Grande. In South Africa, surface processing operations have restarted and importing Mponeng underground mine started to ramp up on April 15 and is now operating at around 50% of production capacity.

Cerro Vanguardia is processing stockpiles and operating at near-planned production rates. and Serra Grande in Brazil has since restarted and is back to operating at normalized levels. As you can see from this slide, AGA stepped up our humanitarian efforts across all of our host countries, working with governments and alongside local communities to stop the COVID-19 spread.

There’s more work to be done, but I’m very proud of the approach and contributions we’ve made from the ground level up in every country where we’re operating.

And with that, I’d like to hand over to Christine to cover the financials.

Christine Ramon
Chief Financial Officer

Thanks, Kelvin. Good day, everyone. I’m on Slide 13, which deals with the comparison of key metrics. We’ve again delivered a solid operational and financial performance from Q1, despite the COVID-19-related suspensions, which impacted the latter part of the quarter and the front-end quarter two.

Despite the accounting treatment of our South African portfolio as discontinued operations, we’ll talk to the group as a whole to make comparisons against last year’s performance easier. Production was 5% lower year-on-year, with cash costs 3% higher and all-in sustaining costs at 4%.

Excluding the 11,000 ounces COVID-19 impacts, production would have been 3% down on last year, with the remaining shortfalls relating to the lost ounces from Morila and Sadiola due to these operations reaching end of life. We saw stellar results from Geita, Kibali and Iduapriem, as well as 19,000 preproduction ounces from Obuasi, which helped cushion the impacts of lower production in Brazil, Argentina, South Africa and Australia.

The stronger gold price, which was up 23%, as well as weaker operating currencies, helped us to deliver 64% improvements in adjusted EBITDA and 227% increase in cash flow from operating activities to $219 million. But the most significant improvement came from free cash flow generation, which at $4 million was a vast improvement on the $109 million outflow for the same period last year, despite being impacted by working capital movements, interest, taxation, and the continued cash lockup in the DRC.

This is especially noteworthy when you consider the additional capital spend during the quarter. The underlying cash generation of the business is exceptionally strong, with all operating regions making a meaningful contribution. We received $25 million in dividends from Kibali for the quarter and our cumulative attributable share of cash balances in country were $252 million at the end of the quarter.

While it’s important to note that the cash is available for use at site, if needed, Barrick continues to engage with the DRC government regarding the 2018 Mining Code and the cash repatriation.

Non-sustaining CapEx for the quarter of $19 million included the project capital of $53 million related to Obuasi, $25 million for the Quebradona feasibility study and $9 million for Tropicana Boston Shaker underground project.

Working capital reflected an outflow at quarter end and was impacted by VAT lockups in Tanzania, Argentina export duty, higher gold and process levels as Obuasi ramps up production, higher consumable inventory levels and credit to outflows post year-end. Working capital movements were positive quarter-on-quarter, mainly due to gold refining proceeds received in January for the Brazil operation from gold produced at the end of last year, despite prepayments of $9 million relating to Obuasi.

At the end of the quarter, we had $122 million in outstanding VAT from Tanzania, a net increase of $7 million from year-end. We also have $65 million of historical VAT in the DRC, which was largely steady from year-end.

Looking at the cost performance year-on-year, our cash costs increased by 3% to $814 – apologies, $814 an ounce. There was a favorable impact of $52 an ounce from weaker currency, which more than offset the inflationary pressures that continue to prevail across the emerging economies that we operate in, particularly in Argentina. Costs were adversely impacted by lower-grade and higher royalty, although stockpile increases mitigated the impact to some extent.

Operational efficiency improvements were slightly delayed due to COVID-19. However, this remains a key group focus to mitigate operational cost pressures. All-in sustaining costs in Q1 were 4% higher year-on-year.

And excluding the COVID-19-related impacts of $18 an ounce, the increase was around 2%, which primarily relates to non-cash increase in the rehabilitation provision linked to changes in discount rates. We also saw higher sustaining capital of $10 an ounce, which supports our strategy to improve our operating flexibility through investments in ore reserve development.

Moving on to the balance sheet strategy. Our diverse portfolio and proactive management of our balance sheet has given us very good flexibility during what remains an uncertain time. We’ve continued to delever the balance sheet on the back of stronger cash flows despite soft funding Obuasi and our other growth initiatives.

Our adjusted net debt position was lower by 10%, or $118 million from March 2019, despite the increased dividend payments and was just under $1.6 billion at quarter-end. It’s also pleasing to see our adjusted net debt-to-adjusted EBITDA ratio at 0.085 times, which is well below our targeted ratio of one times through the cycle.

As we’ve said previously, proceeds from the South African asset sale will be applied to further reduce debt. Our liquidity is strong. As Kelvin mentioned, we made up the interest-full draw on our $1.4 billion RCF facility in the second-half of March. Cash and available facilities were around $2 billion at the quarter-end.

Subsequent to the quarter-end, we repaid $700 million bond redemption in mid-April and have kept the balance in our treasury. In addition, in line with our conservative approach of managing through the COVID-19 pandemic, we’ve bolstered our liquidity headroom with a one-year $1 billion standby credit facility, which we secured late last month. That facility can be extended at the participating bank’s discretion.

We currently sit with approximately $2.3 billion in liquidity and headroom, including the new standby facility, and this excludes the Kibali and Sadiola cash. Our credit ratings are unchanged. We have investment-grade ratings from Moody’s and Fitch and a sub-investment-grade rating from S&P. All have a stable outlook, and Moody’s recently reaffirmed our rating following the annual review.

Our cash flow demonstrates the strong leverage we have to both the gold price and currencies. And with prevailing market conditions, we expect strong improvement to cash flow generation this year. We will, of course, look to augment that tailwind with efficiency improvements across the business.

Finally, while we are well placed to manage through this period, both from a portfolio and balance sheet perspective, the fact remains that there is little clarity for anyone on how severe this outbreak will be, how long it will last or what additional measures governments will put in place to flatten the curve.

In line with our conservative posture with respect to managing through COVID-19, we withdrew our guidance on 27th march. In addition to the 11,000 ounces impact of COVID-19 in Q1 and the all-in sustaining cost impact of $18 an ounce, all our mines are now operating normally, other than Mponeng in South Africa, which commenced production to 50% capacity on 4th May. It will continue to produce at that level until current restrictions are lifted. This, in turn, will have a knock-on effect on all-in sustaining costs in Q2.

Our performance for the year-to-date is consistent with our prior guidance. In line with past trends, production is expected to be weighted to the second-half of the year, with Obuasi expected to ramp up through the course of the year.

The timing of the closure of the sale of the South African assets in Sadiola will dictate the impact to production, net debt and other metrics. In the meanwhile, operating costs continue to benefit from the lower oil price, primarily in continental Africa and from weaker local currencies.

These benefits will be somewhat offset by cost headwinds relating to COVID-19 direct impacts and our interventions to provide flexibility and reduce risk across our operations. These include additional logistics costs relating to transporting gold, increased safety stocks on critical consumables, and increased ore pile – ore stockpiles.

We expect all-in sustaining cost to increase on the back of these COVID-19 impacts, as well as our higher sustaining capital spending and our planned increase in all reserve development and underground drilling across our operation, which will improve operating flexibility and extend mine life.

Brazil has also increased spending on the transition to dry stacking at its PFS. Our focus on efficiency improvements, however, will continue to mitigate the rise in all-in sustaining costs.

Growth capital for the year relates to Obuasi, advancing the feasibility study at Quebradona, Gramalote and Tropicana Boston Shaker underground. We are well positioned to see further reductions in debt levels, as we anticipate improved cash flows from our operations, bearing in mind bearing in mind that we are strongly leveraged to the gold price and along with the proceeds from the South African asset sales and cash repatriation from the DRC.

I will now hand over to Sicelo to cover the African region.

S
Sicelo Ntuli
Chief Operating Officer, Africa

Thanks, Christine. Let’s take a high-level look at the Africa operations on Slide #18. Starting with Continental Africa. The region production was 22,000 ounces higher than the first quarter of 2019 at 360,000 ounces.

I’m pleased to announce the continuation of strong performances at Geita, Iduapriem and Kibali. The all-in sustaining cost at $879 an ounce was 9% lower than the first quarter of 2019. As our OE800 program, which targets additional efficiencies, are keeping costs under control. This has helped offset impacts related to inflation and mining scope changes, particularly at Siguiri, as it transitions from soft rock to hard rock blend.

At Geita, production this quarter was the highest in eight years, with gold production at 135,000 ounces and 24% higher than the previous period, which includes the planned maintenance shutdown. This was complemented by improved recoveries as a result of more consistent plant feed. We continue to be satisfied with Geita’s expansion of underground mining activities and exploration success.

I’m also pleased to report that the government of Tanzania has granted consent and issued the mining permit for Geita Hill underground project, which will be a significant contributor to the future of the operation. The Geita Hill underground portal will be positioned on the western side of Geita Hill pit and will target Blocks 1 and 2.

Development is expected to commence in the fourth quarter onwards, after the mining plan has been signed off by the Chief Inspector of Mines at the Mining Commission, subject also to the status of COVID-19 and the mobilization of critical skills on site. This approval is a significant step forward and will unlock an estimated 1.6 million ounces of mineral resource.

At Kibali, another solid quarter with production marginally lower year-on-year as a result of a planned reduction in recovered grade due to the processing of lower-grade material from the KCD and Sessenge pits as per plan.

Iduapriem’s production was 5% higher and the strong performance was underpinned by an increase in grade due to mining higher-grade ore from Blocks 7 and 8, in line with the mining plan.

At Siguiri, gold production was 48,000 ounces, or 2% lower than the previous periods’ production of 49,000 ounces. Total tonnes treated at the mine was 20% higher, confirming that the combination planned upgrades have been successfully completed, with planned crusher and mill throughput successfully achieved and with a consistent hard rock to soft rock planned ratio of 50% achieved.

However, the key issue remaining to be resolved is metallurgical recovery, which resulted in a 22% lower recovered grade when compared to the prior period. Test records confirmed the presence of preg-robbing material in the area – in the ore. And milling of the ore still presents a high-cost gold fraction of material entering the CIL circuit.

We have a plan in place to convert three more tanks to CIL this year and have initiated a cyclone and mill control optimization to address the coarse gold particles issue. We expect this to be resolved by the fourth quarter, with incremental recovery benefits being achieved till then, as improvements in the milling and classification circuits realized.

In South Africa, despite the challenging safety quarter, Mponeng produced 49,000 ounces at an all-in sustaining cost of $1,257 per ounce, 4% below the first quarter of 2019. Production decreased marginally compared to the same quarter last year, mainly due to the extended Christmas break with a later start-up in January.

Mponeng production was also impacted by safety stoppages due to fatalities and the unplanned closer during the latter part of the quarter due to government’s restriction related to COVID-19.

The safe restart of underground operations at Mponeng began with a return of 50% of the staff in line with regulations, as amended on 16th April 2020. The production ramp-up is in progress following the first blast on the 30th of April and hoisting operations commencing on the 4th of May.

A successful COVID 19 readiness compliance audits of AngloGold Ashanti systems and preparedness was conducted by the DMRE on Friday, the 24th of April. Recognized unions have been playing an integral part in the formulation of our COVID-19 response plans right from the beginning.

As employees return to site, the current focus is on increasing screening and surveillance, including health status checks, temperature monitoring, and recent travel history to help facilitate any detection of any cases. Successful operations, however, have to full capacity.

Moving on to Slide #19. The key focus areas for the Africa region are to: firstly intensify focus on safety and health practices, particularly in South Africa; maintain solid performances at Geita, Iduapriem and Kibali; implement recovery plans to claw back some of the South Africa lockdown production losses, while taking advantage of favorable gold price environment; implement the CIL recovery improvement project at Siguiri; proactively manage supply chains and work with host communities and governments to prevent the spread of COVID-19; and finally, maintain focus on increasing ORD and increasing mineral resource to our reserve conversion over the next two to three years.

On the exploration front, at Geita, we are focusing on identifying and increasing underground ore reserves by targeting extensions of Nyankanga underground, Geita Hill underground; and Star & Comet underground ore bodies.

We are also accelerating infill drilling to add more open pit ore reserves at Xanadu and Roberts area. Infill drilling results at Siguiri Block 2 satellite area have confirmed the viable pit design for Saraya and Foulata pits. That looked to provide additional ore resources to further complement the new plant.

We are also accelerating near-mine infill drilling to test for additional hard rock beneath the current pits of Kami-Tubani and Bidini. At Iduapriem, the grilling continues along the extensions of the reef and other satellite targets of Block 1 and Block 5 Northeast extension. At Kibali, ongoing Brownfields and Greenfields exploration opportunities also bode well for the mine to replace its reserve depletion again this year.

In conclusion, we remain focused on improving margins, managing our risk profiles and instilling the culture of learning and improvement across our sites.

Over to you, Ludwig. Thank you.

L
Ludwig Eybers
Chief Operating Officer, International

Thanks, Sicelo. We’re on Slide 21. The International operations had a demanding first quarter. In January, we had to deal with heaviest rains in over 100 years in Brazil, along with the introduction of new underground support standards of Cuiaba and the adoption of new hygiene and social distancing practices resulting from COVID-19. This is reflected in the gold production for Americas.

Locally, the gold production at AGA Mineracao was 10% lower than in the corresponding quarter in 2019. This reduction was largely due to the introduction of new underground support standard and a new mining sequence at Cuiaba, which was recommended by global experts to address suddenly different ground conditions in the deeper levels. This required additional meshing with bolting, with slight access to the high-grade ore.

However, we believe that the safety critical issue has now been addressed and we can now focus on improving our efficiencies. While I’m always reluctant to comment on safety, it is pleasing to report that the all-in frequency rate for Brazil improved by almost 50% from the previous quarter. As I mentioned earlier, unusual heavy rains impacted gold production.

In Belo Horizonte, we saw more than 100 millimeters of rain over 24 hours in late January. In the state of Minas Gerais, at least 70 people die and about 46,000 people lost their homes. Some of these are our employees. The floods prevented transport of employees to the mines for almost five days and wet weather slowed production in our Rosalino open pit at CdS. The combination of these inefficiencies and high inflation resulted in cash cost increasing 14% year-on-year, which was partially offset by the weaker exchange rate.

On a positive note, at Cuiaba, Cuiaba achieved the highest total development meters in its history during the quarter, which was helped by a new record from the contracted development in March. The impact of these improvements will not be immediate, but it’s critical for us to reach the high-grade main ore body in the deeper levels of the mine.

Then in Brazil, Serra Grande mine was stopped after the COVID-19 lockdown was declared on March 26. The site received overwhelming support from the local research community, which issued a municipal decree to allow the operation to restart on April 1, demonstrating the importance of having a close relationship with local communities.

Cerro Vanguardia in Argentina experienced similar shutdown after a presidential decree to stop production on March 20. We were able to restart the mine operations on April 6 after constructive engagement with the federal government, chairman of mines and local unions. We have since started the open pits and expect underground mining to follow soon.

Resulting gold production at 45,000 ounces was 30% lower year-on-year, which is in line with the life of mine plan. The Australian operations had a strong quarter and a new management team at Sunrise Dam delivered production in line with the mine plan with exploration, drilling and development ahead of plan.

As I previously flagged, a key focus for Sunrise Dam in 2020 is to deliver the development and the drilling needed to grow its ore reserve and improve flexibility. We are currently on track with that information.

Tropicana produced 73,000 ounces, which reflects the planned 50% drop in production after we’ve completed the grade streaming in late 2019. All mines from Havana South, Boston Shaker and Havana 2 pit was separated by stockpile feed to fill the mill and mining is shifted to waste stripping to the future Havana Stage 1 cutback.

The development of the new Boston Shaker underground mine remains on track to begin production in H2 2020, and underground infrastructure remains on schedule. Tropicana gold production reached 2 million ounces milestone during the quarter, just seven years after the mine poured its first gold. It’s worth noting that the mine was started with ore reserves of 3.3 million ounces and it’s – in current PFS, remaining 4.9 ounces of resource and 3.0 million ounce of reserves attributable.

Next slide. I would like to reiterate that our focus remains on increasing ore reserve development and reserve conversion at all our underground sites. Increasing development is critical for us to establish underground drilling platforms and increase production flexibility. This will not only give us better resource confidence and improve productivity, but also gradually grow reserves and extend lots of mines over the next two years.

Sunrise Dam completed the comprehensive drilling program in Q1 in both extension and added new infrastructure targets, and the team is incorporating these results into new geological models. In Brazil, drilling has continued at all sites, returning positive intersections near existing underground development in CdS 1 and also satellite targets closer to the main ore body at Cuiaba. We continue to see encouraging emphasis with [indiscernible] at Serra Grande and expect to start mining these later in 2020.

On Project Quebradona, feasibility study is progressing well and a national environmental licensing authority completed the site evaluation as part of the environmental impact study. The Gramalote joint venture suspended drilling after the declaration of a national state of emergency and quarantine by the Colombian government. Work is still bogey usually at both projects. However, there may be a delay in delivering both of these feasibility studies by year-end.

In conclusion, we’ve seen stable performance from the assets, including a steady improvement in ore reserve development and drilling across the portfolio. With many of the initial COVID-19 challenges behind us, we will be turning our attention to our operational excellence program to deliver additional cost and productivity improvements.

With that, I’ll hand over to Graham, who will talk about Obuasi.

G
Graham Ehm

Thank you, Ludwig. I’m on Slide 34. The Obuasi project continued to make good progress following the first gold pour in December last year despite the country responses and restrictions that have been implemented in response to the COVID-19 pandemic. The ramp-up of Phase I operations to 2,000 tonnes per day has progressed well. The plant achieved the design parameters by the end of the quarter and plant run time progressively improved as commissioning issues associated with the refurbished plant were resolved.

From a geology perspective, you would recall that last year we added 1.3 million ounces in reserves at Obuasi We have continued with the grade control and the infill drilling programs, and the results have confirmed that the resource model, and on several sections, we’re seeing improvements in grade and tonnage I think this is an important point as one starts to move into the commencement of operations for a redeveloped project.

This quarter, we progressed drilling at Block 10 and have seen some rather spectacular intercepts in the first sections, including 63 meters at 22 grams a tonne and nine meters at 10.5 grams per tonne.

In mining, international travel restrictions and the encouragement by home countries for expatriates to return home has had some impact on the mining operation. Some key expatriate contractors have returned home, though many have remained on site. Mining contractors have been extremely supportive and most skilled operators continue to work quite productively on site. As a result, the mine’s currently operating at about 80% capacity.

We’re monitoring the domestic and international travel situation very closely and are looking for the earliest opportunity to rotate crews and get back to full strength As a result of the uncertainties around COVID, the declaration of Phase 1 commercial production is now expected to be in the third quarter of 2020.

On Slide 25. With the Phase 1 refurbishment and construction completed, we are now focused on Phase 2. The objective of Phase 2 is to establish an operating capacity of 4,000 tonnes per day. Phase 2 reached 55% completion at the end of the quarter. of the quarter Concrete works, structural steel erection, mechanical equipment installation and timing facility earthworks have all progressed well. Refurbishment of the underground materials handling system and installation of new pump stations are also progressing well.

While procurement is almost complete, some manufacturing and deliveries have been delayed due to lockdowns in supply countries. While international travel restrictions and temporary lockdowns have also hampered mobilization of some political critical skills. The areas that are most affected are the KRS shaft, which is required to increase mining capacity to 4,000 tonnes per day, and the SAG/ball mill installation and plant instrumentation and controls, which are required for the process plant to achieve 4,000 tonnes per day.

Based on current circumstances, we expected that Phase 2 commissioning and ramp up will be delayed by about three months to late quarter one 2021. Please note that the COVID delay that I’ve discussed is three months in a 20-year project, and we’re delivering the project into a high gold price market compared with that in 2018, when the project was first committed.

With respect to costs, we looked at the impact of the delays on the overall capital cost and managed these delays within the project contingency Therefore, the project remains on budget.

With that, I’ll hand back to Kelvin to conclude.

K
Kelvin Dushnisky
Chief Executive Officer

Thank you, Graham. To wrap up, our strategy remains clear and we continue to execute on our key objectives Our historic and ongoing focus on ESG is paying dividends, as demonstrated in the fight against COVID-19, and we’re approaching the COVID-19 operating landscape conservatively from an operating and financial perspective.

We’re making good progress on streamlining the portfolio and aim to close both ongoing transactions this quarter. We’re generating strong cash flow, and we’re working to ensure that we can safely keep delivering strong all-in sustaining cost margins, especially with the higher gold price.

Leverage is below our target level, and is improving further, given the strong fundamentals in place You just heard from Graham, Obuasi remains on track even with the mining movement in its ramp-up schedule.

We expect positive results from the important ore reserve development and reserve conversion investment we’re making in our key ore bodies, both in terms of extending mine lives and creating greater operating flexibility, and will remain disciplined in managing costs and capital, taking a prudent approach in operating the business. Our aim is unchanged, is to build a solid, predictable business that delivers value through the cycle. So thank you very much.

And with that, we can open up to questions.

Operator

Thank you very much, sir. [Operator Instructions] The first question comes from James Bell with RBC Capital Markets.

J
James Bell
RBC Capital Markets

Question on margins and free cash flow. So when I look at your all-in margin, it looks relatively healthy, but obviously free cash flow was lower than that would imply. I just wonder, when you look at your all-in cost profile going forward and your projected free cash flow, is there anything we should be thinking about in terms of flow back from what we’ve seen in Q1?

And secondly, in terms of the actual all-in cost itself, do you feel that, that metric is a suitable one to be judging the cash generation potential of the business?

K
Kelvin Dushnisky
Chief Executive Officer

James, it’s Kelvin. I apologize. I lost the first part of your question. Hopefully, may have just been on my end. But in terms of the all-in sustaining cost and the translation to free cash flow, Christine, maybe you can respond to that. And if I miss anything, at the start of James’ question, we can come back to it, please.

Christine Ramon
Chief Financial Officer

Okay. Thanks, Kelvin, and hi, James. So I also lost the first part of your question. But I think I get on what you’re getting at and will have come back in the second half So I think, firstly, just for the benefits of everyone to actually run through the items from all-in – the all-in cost and the implied margin to free cash flow, I think, one looks at the items that attracted that difference is running down the list of working capital, tax, interest and then the Kibali cash buildup.

So when one looks at working capital, we did see a large trade creditor’s outflow relating to year-end payments that came through, that was about $82 million We saw an increase in inventory and half of $31 million, half of that’s related to COVID-19 impact in terms of us building up safety stock and stockpiles for safety stocks for consumables.

And then we also saw increased Obuasi and Sadiola process And then when one looks at the third element of working capital, it’s trade receivable. Half of that’s related to Obuasi fee payment, prolonged lead items and then the related to the VAC [ph] holdup that we saw. Tax certainly was higher at $75 million. The interest of [indiscernible] and then we saw $57 million cash buildup relating to Kibali.

In terms of what one would expect moving forward into the year, I think, bear in mind that free cash flow generation is expected to improve, not only because of the higher gold price and efficiency improvements that we are expecting, but production is weighted to the second-half of the year, similar to in the past. So there you would expect to see improvement in free cash flow generation.

As regards working capital, I think, specifically, yes, we do expect to see unwind in the second half of the year, and so some of that will come back.

K
Kelvin Dushnisky
Chief Executive Officer

Thanks, Christine And James, just a point of summary, and again, apologies for missing the start of the question But I think longer-term, all-in cost is a good measure, so we’re addressing a longer-term cash conversion And to summarize, the operating cash flow is very strong and we’re working on releasing that cache lockup issues with that and DRC and care maintenance. So thanks for that. Thanks, Christine.

J
James Bell
RBC Capital Markets

That’s great. And just one more, if I may on Tanzania. You’ve got ongoing ORD work or reserve development going on at Geita and that could yield some pretty interesting results this year. Have you had – I realized with COVID-19 seems to probably start down in May. But have you had any more discussions with the Tanzanian government as to the ownership structure of Geita following on from, obviously, Barrick’s agreement with the government around the Acacia assets?

K
Kelvin Dushnisky
Chief Executive Officer

Yes, James, two things First of all, thank you. I think some very good news to start in Tanzania relates to the permit we received in the quarter for Geita Hills underground That was – that’s key for us And it’s good that, the government processes are working there favorably for us, and we continue to maintain very good relationships at the local level and working on that up Lines of communication are open locally and state and federal level.

There has been no discussions regarding anything other than that and anything kind of agreement context, we continue to work hard locally. We’re seen as, I think, a respectable taxpayer in Tanzania and all those things. So nothing’s changed as far as that goes.

And even in the COVID-19, we’re able to continue with our drilling work on the ground as well. And Sicelo, you may want to add a little color to that, if there’s anything else that I’d left unanswered.

S
Sicelo Ntuli
Chief Operating Officer, Africa

No, I think you’ve mentioned all of it, Kelvin. Thanks.

K
Kelvin Dushnisky
Chief Executive Officer

Business as usual right now in Tanzania, James.

J
James Bell
RBC Capital Markets

Okay. But there’s still an expectation that there will be some discussions around the ownership structure of Geita this year? Or do you feel like it’s business as usual and actually the ownership structure will likely remain as it is for the foreseeable

K
Kelvin Dushnisky
Chief Executive Officer

Well, I don’t anticipate any change at this point. As I said, we’ve had dialogue on lots of things in Tanzania. We’re in no direct discussions regarding any ownership changes in that regard. So at this point, our plans are business as usual at Geita.

J
James Bell
RBC Capital Markets

Perfect. Thanks for taking my questions.

K
Kelvin Dushnisky
Chief Executive Officer

You’re welcome. Thank you.

Operator

Thank you. The next question comes from Shilan Modi of UBS.

S
Shilan Modi
UBS

[Technical Difficulty]

Operator

Hello, Shilan, we are not hearing you clearly. Can please repeat that.

S
Shilan Modi
UBS

Hi. Can you hear me clearly now.?

Operator

That is much better. Thank you.

S
Shilan Modi
UBS

Okay. Afternoon, team. Can you – given the decision to keep CVSA, can you give us what you think the outlook is for the asset? On the last set of numbers, I think, the asset has about a four-year life remaining?

K
Kelvin Dushnisky
Chief Executive Officer

Yes.

S
Shilan Modi
UBS

Secondly, how does your credit rating change with the divestments that you’ve announced? And then I noticed your CapEx declined by $63 million over sequential quarters. On the face of it, it looks like you’re in cash preservation mode in some form. Can you maybe talk to that?

And then the last question. What is the annual cost of reserve – resource to reserve conversion across the group for the next three years? You can give it in dollar million or dollar bond?

K
Kelvin Dushnisky
Chief Executive Officer

Okay. Well, thank you all. I’ll start with those and then ask colleagues to chime in as appropriate. Starting with CVSA. When we initiated that process about a year ago, the reason for it was CVSA, it’s always been a great asset for the company. So – but you may recall, we made the decision strategically that to the extent, it’s sensible to do. So we want to focus on cluster of – clusters of assets and critical mass, and we want to continue to build on that. So – and with limited capital, you’ve got to make those decisions, hence process around CVSA.

Having said that, we were also clear, no fire sales. And so, when we went through the process, it was certainly an active process, comprehensive. There are a number of bids surface, but none that we thought reflect full value, especially when you consider CVSA at $1,500 gold price will generate in the range of $70 million in free cash flow, generating good cash now and will continue, you’re right.

The mine life presently around four years. But as Ludwig intimated, it’s also an asset now, where we’re going to spend a little more on reserves development and in Brownfields drilling at CVSA. And we’re hopeful that we can actually extend that out a little So that’s the objective for CVSA.

The other thing with it is, it’s got a very strong operating team. And so as we’ve gone through the process, it was important that, when we made the decision, we’re going to keep it. We want to make sure that that team stays motivated, there’s high level of talent there. And so, again, we’re happy to keep it in the family. And we’re doing that for all the right reasons.

The second comment, we’ll come back to regarding the credit rating. The CapEx, no, we’re not conserving cash. This is just about sequencing and consistent with the plan for the year. The cost of the reserve conversion, we had – as we indicated at the – in February with our results, we’ve been targeting in the range of $30 an ounce for ORD, both underground development and reserve conversion this year.

So far that remains on track. I think in Q1, we’re around $10 an ounce. Someone will correct me if I’m wrong on that, but just to give you a sense. So that hasn’t changed. We’ll see as we go through the year. We’re continuing to be able to target and kind of zero win strategically where we want to do that drilling.

And we mentioned Geita, Ludwig, I think, indicated the Sunrise Dam, Brazil as well Iduapriem. So we’re able to continue to do that. And we think that will disproportionately add value, both in terms of mine flexibility and extending reserve life as well in doing so.

And the other question, and I apologize if I missed any, but was regarding credit rating. And Christine, you may want to comment on that.

Christine Ramon
Chief Financial Officer

Yes. Thanks, Kelvin. Apologies I thought one of the questions on CapEx was, what was the change from Q4 to Q1. So if I can just give best information as well. So from Q4 to Q1, we saw the CapEx dropped by $40 million. And it was $262 million in Q4 last year and in total CapEx, it’s $199 million in Q1. And the drop was split really between growth CapEx and sustaining capital between $2 million drop in sustaining capital in Q1 and in the balance was really the drop in growth capital in Q1.

As regards to the credit rating, in particular, we do not anticipate the South African asset disposal to have an impact on our credit rating. I think, bear in mind that South Africa constitutes a relatively small component of our overall production and EBITDA. So we’re not anticipating any change to our credit rating at the consequence of the asset disposal.

S
Shilan Modi
UBS

Okay. Thanks very much.

K
Kelvin Dushnisky
Chief Executive Officer

Thanks for the questions.

Operator

[Operator Instructions] The next question comes from Richard Hatch of Berenberg Capital Markets.

R
Richard Hatch
Joh. Berenberg, Gossler & Co. KG

Thanks very much. A couple of questions. First one, just on Obuasi. Would you be able just to expand a little bit more on where you see the biggest risks in terms of delivering on your plan there?

Second question is just on inflation. You talked to it earlier in the call, but I just wonder whether you might be able to quantify kind of what kind of mining cost inflation you’re seeing kind of globally, and I appreciate you’re probably seeing more in certain jurisdictions than others. But if you’re able to kind of put some kind of handle on that?

And then thirdly, just on returns to shareholders. I completely understand you raised your dividend earlier this year. But also with the generation of free cash flow expected to pick up in the second-half, plus net debt-to-EBITDA moving below your one times target. What’s your thought process on returns to shareholders into the medium-term? Thanks.

K
Kelvin Dushnisky
Chief Executive Officer

Thanks. Well, thank you, Richard. Look, if you don’t mind, I’ll work backwards on your questions. The – in terms of dividends, as you may know, Richard, our dividend policy is 10% – payout 10% of free cash flow before growth capital. And as we’re working hard to increase free cash flow generation, as you saw at the end of last year, and as we’re doing this quarter, we will by definition, be paying out at an increased dividend presuming everything stayed, gold price day supportive, et cetera, et cetera. So that’s the objective.

Now, having said that, and it’s a Board decision. But there’s unanimity in the Board discussion that with time as we kind of move through the phase of bringing, ramping up Obuasi and so forth, structurally, would we like to increase the dividend policy at time? Absolutely, we will.

But we want to make sure we do that prudently and no lurching and so kind of sure and steady as far as that goes. In the meanwhile, take advantage of these good gold prices and the margin expansion and continue to increase dividends, again, through the existing formula.

And if you don’t mind, what I’d like to do is on Obuasi, I’ll ask Graham to comment on where he sees the areas of risks and how we’re managing them. And then Christine will come back to yourself on the inflation, what we’re seeing globally, how we’re managing it. And feel free to have Ludwig and Sicelo chime in it, if you’d like. But maybe we’ll start with Graham on Obuasi.

G
Graham Ehm

Thanks, Kelvin. Thanks, Richard. In answering your question in regard to delivery risk on the project now, let me say that it’s almost entirely COVID risk now. The project is at a point where Phase 2 is up at sort of 55% completion, procurement is virtually all complete. Contracting, all complete So in terms of setting things up to deliver on the project, I think, we’re in very good shape.

From a COVID point of view, let me explain it in a few different ways. In terms of operations, it’s mostly to do with the mining expatriate skilled workforce. In this quarter, we’ve experienced the shortage of those skills, which is limiting our production to about 80%. We’re also limited to being able to rotate the expat crews And this is true for most expatriate workforces globally.

And as long as that we’ve got a workforce that are committed to continue to work, but we’ll look for every opportunity to be able to rotate that crew and get that crew back up to full strength.

In terms of the project itself, it’s two parts, would be materials delivery and manufacture. Critical path through the mills with the manufacturer of the mill heads and bearings in China. That was delayed, but has now been completed and those components are on the wharf ready for dispatch. The global shipping and transport is in a state of disarray. So we’re not exactly sure when those components will get to site.

There are a few other material components. One is coming up from South Africa. That’s the case of manufacturing, getting going again in South Africa and then the transport. The other key issue for construction is around the key skills required as we get to the pointy end of construction. And by there, I mean, the biggest impact is on the carbon shaft, installing the winding equipment and instrumentation and controls.

So we would need to get those skills back to site. The procurement for all of that and the engineering is all complete. We need to get those people back to site. And the other key one would be on the instrumentation controls for PLCs and starter, getting those people on site. There’s much work being done off-site actually in Perth and finish that work. We need to get people back to site.

So the issues are around manufacturing and getting key skills to site. And the timing on that will be all dependent on how quickly countries open up their borders for international travel. Does that answers your question?

R
Richard Hatch
Joh. Berenberg, Gossler & Co. KG

Yes, very much. Very helpful. Thank you.

Christine Ramon
Chief Financial Officer

And if I could answer the question on the cost inflation that we’ve seen. It’s Christine speaking.

R
Richard Hatch
Joh. Berenberg, Gossler & Co. KG

Thanks, Christine.

Christine Ramon
Chief Financial Officer

Hi. So the cost inflation that we’ve seen has averaged at around 4.5% across the group. I think, if one looks at the big buckets of spend categories in our group is labor, contractors, costs and receivables of 25% each. And we’ve been able to across all of those categories contain increases in costs. I think, in particular, in certain jurisdictions like Argentina and South Africa, we’ve seen higher cost inflation for Argentina. The inflation has averaged around 25% to 30%; in South Africa, at around 8%.

And however, inflation because in the large part of Continental Africa and in Australia, you’re really looking at more dollar-based costs. And so there, we were actually able to contain the increases as well. And so overall, it does average at the 4.5% for the group.

R
Richard Hatch
Joh. Berenberg, Gossler & Co. KG

Okay. Very helpful. Thanks all to your answers and wishing you all the best.

K
Kelvin Dushnisky
Chief Executive Officer

Thank you very much.

Operator

Thank you. Sir, that was the final question. I can now hand over back to Kelvin for closing comments?

K
Kelvin Dushnisky
Chief Executive Officer

Well, thank you very much, operator, and thanks again, everyone, for joining the call today. We – I’ll just wrap up very quickly. End result, listen, the business is performing very well. We’re generating strong cash flow The – our liquidity is strong and we’re in very good position that way. And we’re managing the COVID-19 situation, I think, I’m very proud of our teams have responded The relationships that we have on the ground and all the way up to dealing with senior governments are obviously paying dividends. We’re going to continuing to stay focused on that. And, look, we’ll look forward to reporting back with our H1 results in August. And the meanwhile, I hope everyone, you and your family stay safe, and we’ll look forward to speaking to you again soon. So thank you very much.

Operator

Thank you. Ladies and gentlemen, that concludes today’s conference. Thank you for joining us. You may now disconnect your lines.

All Transcripts