Good morning. My name is Chris and I will be your conference operator today. At this time, I would like to welcome everyone to the Keyera Corporation Third Quarter 2018 Results Conference Call. All lines have been placed on mute to prevent any background noise. After the speakers' remarks, there will be a question and answer session. [Operator instructions.] Lavonne Zdunich, Director of Investor Relations, you may begin your conference.

L
Lavonne Zdunich
Director of Investor Relations & Communications

Thank you and good morning. It's my pleasure to welcome you to Keyera's third quarter conference call. With me today I have David Smith, our President and CEO; Steven Kroeker, Senior Vice President and CFO; Brad Lock, Senior Vice President of the Gathering and Processing Business Unit; and Dean Setoguchi, Senior Vice President of the Liquids Business Unit. In a moment David will provide an overview of the quarter, followed by operational updates from Brad and Dean. Steven will provide additional information about our financial results. We will open the call to questions once we have completed our prepared remarks. Before we begin, I would like to remind listeners that some of our comments and answers that we will be providing today speak to future events. These forward-looking statements are given as of today's date and reflect events or outcomes that management currently expects to occur based on their belief about the relevant material factors as well as our understanding of the business and the environment in which we operate. Because forward-looking statements address future events and outcomes, they necessarily involve risks and uncertainties that could cause actual results to differ materially. Some of these risks and uncertainties include general economic, market and business conditions, fluctuations in supply demand, inventory levels and pricing of natural gas, NGLs, isooctane and crude oil, the activities of producers and other industry players, including our joint venture partners and customers, our operating and other costs, the availability and cost of materials, equipment, labor and other services essential for our capital projects, contractor performance, counterparty risk, governmental and regulatory actions or delays, competition for, among other things, business opportunities and capital, and other risks as are more fully set out in our publicly filed disclosure documents available on our website and SEDAR. We encourage you to review the MD&A, which can be found in our 2018 third quarter results published yesterday and is available on our website and on SEDAR. With that, I'll turn it over to David Smith, our President and CEO.

D
David G. Smith
President, CEO & Director

Thank you, Lavonne, and good morning everyone. Yesterday we reported our third quarter financial results, and I am pleased with the overall performance of our integrated business in a challenging environment. Adjusted EBITDA and distributable cash flow both increased in comparison to the same period last year. Net earnings were CAD 35 million for the quarter, similar to the third quarter of 2017. We maintained a low payout ratio of 72% for the quarter and 61% for the year-to-date. Steven will speak more to the financial results later in the call. Keyera continues to execute on our capital program. Since the beginning of the year, we have completed the Base Line terminal, the Keylink and Hull NGL pipeline systems, liquids handling enhancements at our Simonette gas plant, and the Pipestone liquids hub. All of these projects are generating incremental long term fee-for-service cash flows. With increased production from liquids-rich areas in Alberta, our liquids infrastructure and marketing segments are also benefitting. There is high demand for our fractionation, storage, and condensate facilities, and we are transporting more volumes than ever before to end user markets. Keyera is well positioned for continued cash flow growth with our development plans at our Simonette, Wapiti and Pipestone gas plants, and continued expansion of our liquid infrastructure. We are constantly looking for the right opportunities to expand, extend, and enhance our integrated network of facilities. A good example is our proposed KAPS natural gas liquids and condensate pipeline system in northwest Alberta, which Dean will talk about. Keyera has a history of prudent, disciplined capital allocation, which we believe will continue to generate cash flow growth and long term shareholder value. With that, Brad Lock will now discuss our gathering and processing business unit.

B
Bradley W. Lock

Thanks, David. The gathering and processing business unit delivered an operating margin of CAD 64 million in the third quarter of 2018, with gross processing throughput averaging 1.48 billion cubic feet per day, virtually unchanged compared to the same period last year. Volume growth at both the Simonette and Alder Flats gas plants was offset by volume declines at certain facilities, particularly the Rimbey and Minnehik Buck Lake gas plants, where natural gas prices and lower producer activity have impacted gross processing throughput. During the quarter, we continued to progress our projects in the liquids-rich Montney and Duvernay regions of northwest Alberta to meet the growing needs of producers in the area. At our Simonette gas plant, civil work began to prepare for the acid gas injection and gas processing expansions. In the Wapiti region, we are fast approaching mechanical completion for phase 1 of the gas plant and gathering system, with all major equipment being received and installed at site. Engineering work and procurement of long lead items continues for phase 2 of the gas plant and the North Wapiti pipeline system. In September, the Pipestone liquids hub became operational and is now generating incremental margin, while development of the Pipestone gas plant continues. These projects will begin to add meaningful cash flow beginning in mid-2019 when phase 1 of the Wapiti gas plant is completed, and will continue to build as we complete the North Wapiti pipeline system and Simonette expansions in the second half of the '19, followed by phase 2 of the Wapiti Gas plant in mid-2020 and the Pipestone gas plant in 2021. These 3 gas plants support some of the most attractive geological developments in the Western Canada Sedimentary Basin, where producer economics are driven by the strong value of condensate rather than natural gas. Our long term plan will be to interconnect these 3 gas plants, providing producers with increased flexibility and reliability with 950 million cubic feet per day of sour gas processing capacity and 90,000 barrels a day of condensate handling facilities. I will now turn it over to Dean to discuss the liquids business unit.

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

Thanks, Brad. We're pleased with the performance of the liquids business unit in the third quarter of 2018, with solid results from our infrastructure and marketing segments. Operating margin for liquids infrastructure was a record CAD 82 million, up 15% from the same quarter last year. These results were largely driven by increased demand for our condensate services and incremental margin from new assets, including the Norlite pipeline and the Base Line terminal.During the quarter, 5 tanks were completed and, in October, the final tank was placed into service. Keyera will realize the full benefit of this asset in 2019, which is fully contracted with take or pay contracts up to 10 years in length. With increased production from the liquids-rich areas in Alberta, we had strong demand for many of our liquids infrastructure assets and services. Our fractionators at Fort Saskatchewan operated near capacity. Utilization of our storage caverns were high, and we handled record volumes through our condensate system.We are pleased to have completed the South Grand Rapids diluent pipeline. This new pipeline provides our customers with additional capacity, flexibility, and reliability between Edmonton and Fort Saskatchewan, and positions Keyera for future growth. As producers continue to focus on liquids-rich Montney and Duvernay developments in northwestern Alberta, we recognized the industry's need for a competitive NGL transportation solution from the area to Fort Saskatchewan, Alberta's NGL hub. In the fourth quarter of 2018, we entered into a 50/50 joint venture agreement with Wolf Midstream to develop the Key Access Pipeline System, KAPS, a proposed liquids gathering system that would include a pipeline dedicated to transporting natural gas liquids and a second pipeline dedicated to condensate service. We continue to work with producers in the area on this egress solution and expect a final investment decision in 2019, subject to obtaining sufficient customer support and final cost estimates. Turning to our marketing segment, we generated realized margin of CAD 43 million in the third quarter compared to CAD 10 million in the same period last year. We continue to benefit from a high contribution from our isooctane sales, as well as contributions from our Oklahoma liquids terminal acquired in June. Our condensate business has also generated strong results as we move more volumes through our system to meet the growing needs of our oil sands producers. Our AEF facility has operated very well in 2018 and continues to maintain high utilization rates. To help ensure continued reliability and high utilization of the facility, we recently shut down AEF for preventative maintenance. The outage is not expected to have a material financial impact, as demand and margins for isooctane are typically lower as we approach winter. We expect AEF to resume full operations by mid-November. Looking to the fourth quarter, we will be moving propane inventory to take advantage of the high demand winter months. We'll leverage our Josephburg rail terminal and marketing expertise to move propane to the highest value markets. As always, rail service is a key element of this strategy, and we are working with the railways to achieve expected service levels. Our marketing business continues to be a strong contributor to Keyera's success. Year-to-date, it has generated over CAD 190 million in realized margin, providing cash flow that can be reinvested to help fund our capital program. With that, I'll turn it over to Steven to discuss the financial results in more detail.

S
Steven B. Kroeker
Senior VP & CFO

Thank you, Dean. As mentioned earlier, we had a successful quarter as our 3 integrated businesses combined to deliver solid results compared to the same period last year.The gathering and processing business segment delivered operating margin of CAD 64 million, slightly down from the CAD 69 million recorded in the same period last year. Reduced producer activity in certain areas combined with higher operating costs lowered our operating margin at some facilities.The liquids infrastructure business segment posted a strong quarter compared to the third quarter of 2017, due to full quarter results for the Norlite pipeline and partial startup results for Base Line terminal. As well, there was overall growth in demand for Keyera's condensate network, including our transportation and storage services. The marketing segment's realized margin was CAD 43 million versus CAD 10 million in the third quarter of 2017, as isooctane's contribution benefitted from short term demand that carried over from the second quarter into July. Our liquids blending and condensate businesses were also strong contributors to realized margin. As a result of our integrated business performing well during the quarter, adjusted EBITDA increased 16% over the same quarter last year, while distributable cash flow was 7% higher on a per share basis. Our trailing 12 months' adjusted EBITDA was CAD 756 million. Net earnings were CAD 35 million, and included CAD 63 million in impairment expenses as we reduced the value of the Minnehik Buck Lake and Zeta Creek gas plants due to reduced drilling activity and corresponding throughput volumes at these facilities. Looking ahead to 2019, we expect a full year cash flow contribution from various projects, including the Base Line terminal, the Pipestone liquids hub, the Simonette liquids handling expansion project, the Keylink NGL gathering system, and the Oklahoma liquids terminal. In addition, we expect the first phase of our Wapiti gas plant to be generating incremental cash flow by mid-2019, followed by cash flow from the North Wapiti pipeline system and the Simonette expansion. Year-to-date, our maintenance capital is CAD 37 million. For 2019, we expect maintenance capital to range between CAD 100 million and CAD 110 million, which is unusually high for a year when we are not conducting a turnaround at AEF. The higher range includes approximately CAD 50 million in plant turnarounds planned at our Rimbey, Pembina North, Cynthia, and Ricinus gas plants, but also includes various nonrecurring costs. For example, it includes nonrecurring maintenance capital at our Keyera Fort Saskatchewan fractionator, some equipment procurement costs in advance of our turnaround of AEF in 2020, and a change out of one of our more expensive catalysts at AEF, which has a useful life of 4 to 5 years. In 2020, AEF is expected to complete a full turnaround. Year-to-date, our cash taxes are CAD 25 million. Given our deferred partnership structure, our strong operating results year-to-date, and the timing of when assets related to our significant capital expenditures become available for use, we expect cash taxes for 2019 to increase to between CAD 100 million and CAD 110 million before coming back down in 2020 to less than CAD 20 million. Our cash tax estimates assume our business performs as planned and our capital projects are completed as expected. As a reminder, in 2019 we expect approximately CAD 950 million of new assets in the gathering and processing segment to become available for use. And over 2020 and 2021, we expect a further CAD 750 million of new assets in the gathering and processing segment to become available for use. The tax pools related to these expected new assets have attractive capital costs allowance claim rates, which helps reduce cash taxes. With a net debt to EBITDA ratio of 2.7 times at the end of the third quarter and a payout ratio of 61% year-to-date, Keyera continues to be well positioned to fund its ongoing capital program. In turn, the capital program is expected to add meaningful incremental EBITDA to Keyera in each of the new three years. That concludes my remarks. David?

D
David G. Smith
President, CEO & Director

Thanks, Steven. Keyera continues to serve our customers' needs. And as our third quarter results demonstrate, demand for our products and services is healthy. Although we're disappointed with the continued low drilling activity around some of our gathering and processing facilities, we are seeing signs of recovery in natural gas prices, and we're encouraged by Shell's decision to proceed with their West Coast LNG project and Imperial's decision to proceed with their Aspen oil sands project. Our facilities are well positioned to profit both short term and long term as the industry activity recovers. We continue to have a disciplined strategy focusing on maximizing cash flow from our existing assets, building a strong footprint in the liquids-rich Montney and Duvernay developments in northwestern Alberta, and pursuing opportunities to expand and integrate our value chain in the Western Canada Sedimentary Basin and the U.S. In 2019, we are planning to invest growth capital of between CAD 800 million and CAD 900 million, primarily focused on projects already underway that support these strategies. Keyera's strong balance sheet and excess distributable cash flow position us well to fund this current capital program. We look forward to a strong finish in 2018 and cash flow growth in 2019 with a continued focus on operational excellence and project execution. On behalf of Keyera's directors and management team, I would like to thank our employees, customers, shareholders, and other stakeholders for their continued support. With that, I'll turn it back over to the operator. Please go ahead with questions.

Operator

[Operator instructions.] Your first question comes from Linda Ezergailis of TD Securities.

L
Linda Ezergailis
Research Analyst

I'm wondering if you could help us understand a little bit more about your proposed KAPS project. Specifically, I'm wondering what does each partner bring to the JV. How might we think of the time line beyond FID to get to an in-service date and key milestones? And I realize there might be some sensitivities to providing any sort of ballpark cost estimates, but to the extent that you can give us some parameters around that, that would be helpful.

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

Hi, Linda. It's Dean. That's a lot of questions. But we are very excited about our KAPS project. Our partner is Wolf, and obviously you probably know some things about Wolf. And you can check out their website, I guess, to find out more about the company.But really, the principals of that company are the guys who built the Vantage pipeline, so pretty impressive work on what they did there, crossing 3 jurisdictions from the U.S. into Saskatchewan and Alberta. So they bring a lot of expertise from that front. And they're a very good partner to work with, so we're very pleased to have them as a partner. In terms of overall cost, we are working towards a class 3 estimate, and we will have that early in the next year. So right now we don't have any sort of numbers that we're prepared to share, but we're continuing to refine our estimates. And part of that is our initial scoping of the pipeline would take it out to our Pipestone gas plant, but we are evaluating interest beyond that to the northwest. But the pipeline is expected to be just in Alberta.

L
Linda Ezergailis
Research Analyst

That's helpful.

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

Sorry, did I answer -- yes. Did I answer all your questions?

L
Linda Ezergailis
Research Analyst

Yes, a time line as well would be helpful beyond FID.

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

Sure. Yes, the time line would be in service early in 2022, and the bulk of the capital expenditures as laid out today would occur in 2021. So really, it would be after the capital expenditures that we've committed to so far, so beyond that time period. And the projects that we have on the table today, they'll be contributing cash flow to help fund those expenditures out in 2021. So the time line fits in with our capital program and funding needs as well.

L
Linda Ezergailis
Research Analyst

Thank you. And would you expect to get your full customer support in advance of FID, or some sort of minimum threshold and then continue to build up after FID?

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

Yes, we would want enough commitments to establish a base return for this project. And we've often been asked the question of how much volume you need, and that's not an easy answer. And part of it is when the volumes come in the system, because the further you are out on the pipeline the tolls are higher, and it also relates to term and sort of volume and term of commitment. So there's a lot of variables that are involved in terms of how much we need to actually sanction this pipeline.

L
Linda Ezergailis
Research Analyst

Thank you. And just an operational question to understand your expensive catalyst that you're replacing at AEF next year. Is there some sort of modest incremental bump in efficiency that declines over the 4 or 5 years, or is it really just seamless and no material change in operations between the new versus old catalyst?

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

Yes, what happens is that we've actually been very successful in running our facility above nameplate capacity. And over time, though, that creates a bit more wear and tear on the facility. In fact, we just completed one of our longest continuous runtimes in plant history. But again, with that, there's some repair and maintenance that has to be done to keep that -- AEF performing at high utilization rates, so that's why we have to change out the catalyst. And the reason why it's shut down right now, part of it is because we're replacing the dimerization catalyst, and next year we're planning to replace the old flex catalyst. There's different kinds of catalysts that have different expected lives. The good thing about our change out of the old flex catalyst next year is that we don't think we have to shut down the facility to do that.

Operator

Your next question comes from Rob Hope of Scotiabank.

R
Robert Hope
Analyst

Maybe just a follow up question on KAPS. So we appreciate that you could have an origin at Pipestone. Just wondering, will Pipestone have also a connection to another competing pipeline? And do you have a base level of volume commitments secured so far?

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

A Our pipeline is -- our planned pipeline is basically to connect several gas plants up in the Montney-Duvernay, including our own, and connect it into Fort Saskatchewan. And initially, it'll be connected to our KFS facility with plan to connect to other fractionators in Fort Saskatchewan as well to provide a competitive alternative.

R
Robert Hope
Analyst

Thank you. And do you have any commitments to far that you're working off of, or is it relatively open so far?

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

No, Rob, we are just working with customers right now. And we can't disclose, I guess, what we have so far, but we're continuing to work with our customers on those commitments.

R
Robert Hope
Analyst

Okay. Thank you. And then just moving over to maintenance, appreciate the color on the 2019 maintenance number. Just looking over at 2020, though, AEF was north of CAD 50 million a couple years ago, and you also do have some relatively large plants coming up for turnarounds as well. Just wondering, is 2019 indicative of 2020?

S
Steven B. Kroeker
Senior VP & CFO

Yes, it's Steven here. We haven't gone through and done all our estimating yet for 2020, so too early to tell. But directionally, I think you're right in terms of turnarounds at some of our bigger facilities in '20 and our AEF facility, obviously.

D
David G. Smith
President, CEO & Director

Yes, I think --.

R
Robert Hope
Analyst

Thank you.

D
David G. Smith
President, CEO & Director

2020 -- AEF will be in 2020, and that'll be the big one, Rob. I think the significant G&P facilities will be done this year and next year.

Operator

Your next question comes from Ben Pham of BMO.

B
Benjamin Pham
Analyst

Wanted to go back to the KAPS project. And I'm wondering, could you talk about perhaps the positive implications downstream on the fracs, the storage, the marketing? Would this lead to potential expansions downstream? And then when you think about those additional revenue streams, is that part of your base return that you're thinking about, where you might not get the targeted volumes initially but you should be including the additional revenues downstream?

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

Ben, it's Dean again. Well, we have a partner, which is Wolf, 50/50, and this has to -- KAPS has to meet our joint investment hurdles on a standalone basis. But you bring up a very good point, that if this project is sanctioned, it will generate more business and service needs on the downstream side of our business, including fractionation, storage, and also our marketing services as well. So we believe that that will help our entire integrated value chain.

B
Benjamin Pham
Analyst

And anything on the U.S. side, what you have now, what you can do to integrate even maybe North American -- maybe that's a bit of a stretch, but is that something to think about there?

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

Well, today, as you know, we have the Hull rail and truck facility that is pipeline connected into Mont Belvieu. And you've probably seen that the differentials are pretty wide between -- have been very wide between Conway and Mont Belvieu. So again, it's helped our Canadian business by having that high value market outlet for our products, and mainly propane. So we are sort of integrated, some of our U.S. assets, into our business plan already.

B
Benjamin Pham
Analyst

Okay. And a question on the balance sheet. I know, Steven, you mentioned 2.7 times debt to EBITDA. It's a probably the lowest leverage in the Canadian universe. How do you kind of see that trending next year? High CapEx this year, high CapEx next year, are you exceeding the 3 times debt to EBITDA? And if you are, would you be comfortable being able that range?

S
Steven B. Kroeker
Senior VP & CFO

Yes. No, we do see it trending up modestly into 2019, again, new EBITDA coming on throughout '19, full run rates on various assets as well. It'll probably get to that 3-ish time range, in that area. And from that point of view, we'd be comfortable in that kind of range. Historically, I think we've said 2 to 3. But as assets become more and more fee-for-service, it does give us flexibility there. And as well, you're always looking through projects too to see when the rest of the EBITDA is coming too. So I wouldn’t say it's always a hard and fast. I think you always just have to continue to manage it and look forward and see what your forward view is as well.

Operator

Your next question comes from Robert Catellier of CIBC Capital Markets.

R
Robert Catellier

I think you've answered the majority of my questions. Most of them were related to KAPS, but obviously that's an asset that could help your G&P business generally. But that asset aside, what has to happen to get some renewed activity in and around some of the plants in drier gas areas? Simply a question of price, or will some other assets and debottlenecking of the NGTL system help some of those plants?

B
Bradley W. Lock

It's Brad here. I think you've hit on basically the 2 key things. The -- certainly the restrictions in moving gas to market, both through TCPL and some of the other egress points have an impact on AECO pricing, and consequently that has an impact on producers' willingness to drill or ability to drill the drier gas targets that are typically centered in the west central region. I think for that reason is exactly why we've been enhancing our investment in growth in the northwest part of the region where gas price becomes less sensitive. And certainly, as we look forward in time, the growth in volumes at Simonette and Wapiti and Pipestone are going to happen somewhat irrespective of what gas price is, because they're so driven by the condensate side of the business, which remains strong.

R
Robert Catellier

Sorry. Does the recent round of NGL -- NGTL expansions add any market access capabilities to some of the drier gas regions?

B
Bradley W. Lock

Well, I think they call help. I think if you look out over time, the gap between AECO and Henry Hub is continuing to close. It's just a timing that says investments in NGTL often take a long time to kind of reach fruition, so consequently that capacity comes on a little bit at a time. And consequently, the growth -- or the ability to close that gap is slow to evolve. But we're certainly encouraged by the direction it's going. We're also encouraged by some of the additional opportunities that are being presented to grow internal consumption for gas. As you look at coal conversions and things like that, all those help to unlock capacity, getting gas prices a little stronger in Alberta.

D
David G. Smith
President, CEO & Director

Rob, it's Dave here. I just would add one thing. In that west central Alberta area, we've got a very well developed network, obviously. What I would say is that the gas in that area is liquids-rich. It's drier, perhaps, than what you see in the Montney around Grande Prairie, and it doesn't have as much condensate in the liquids as you -- as propane and butane. And so seeing stronger gas prices, seeing stronger propane and butane prices, I think would all be helpful in that area. But the economics of the resource are very good. I think as Brad has pointed out, the challenge for producers has been that they just haven't had the cash flow to reinvest. And if we can see some recovery in those commodity prices, then I think that will lead to more drilling activity in that area. That's certainly what we expect.

R
Robert Catellier

Okay. It doesn't sound like the picture has changed at all. Thank you.

Operator

[Operator instructions.] Your next question comes from Robert Kwan of RBC Capital Markets.

R
Robert Michael Kwan
Analyst

Maybe I can start with volumes on the G&P side. There's been significant performance differential for volumes. Plants like Simonette are doing very well, and then, as you mentioned, kind of the west central stuff not so great. I guess just overall, how have you seen volumes shaping into the first kind of call it 5 weeks of the fourth quarter? But as well, when you look at the plants where you've seen volumes come off, I guess in many ways how much more is there to go, just given this has been a trend for several quarters?

B
Bradley W. Lock

I think certainly one of the things that we've seen and certainly the producers have been communicating is they do see stronger pricing in the winter. And I think even if you look at the AECO trends over the last while, we have seen some stronger pricing for periods. Every time there's a disruption, it tends to be a little bit variable, so there's a fair bit of volatility. But I think starting October 1, there was a strength in pricing, and we actually did see some strength in volumes as producers started to try to capture winter opportunities. I think we're going to see that continue. I think producers continue to look at volumes and say if I had volumes, I may have been holding off on tying them in and turning them on until the strength of winter pricing kicks in. So I think we're going to see some of those. What impact that has over the back half of the fourth quarter and into the first quarter is hard to say. But I certainly believe that there's going to be -- it'll be a more positive situation than we certainly saw through the second and third quarter when the price variability was quite high.

R
Robert Michael Kwan
Analyst

Got it. If I can maybe turn to KAPS, you mentioned you're going to hook into KFS. Is it going to be an open access pipeline, or are you looking only to deliver into KFS?

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

Robert, initially the plan is to tie into KFS. But again, we want a competitive system, and that means it's going to be an open access pipeline.

R
Robert Michael Kwan
Analyst

Okay, got it. Recognizing it was a while ago and the rates are different, I'm just wondering how are you marketing KAPS out to customers, say differently versus ALPS, or can you just compare and contrast the two projects for us here?

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

Well, I think in general, first of all I think our producer customers and also the consumers of spec products would like a competing system. So I think that's first and foremost. We have to be competitive on our tolls, which we believe we are. But we are looking and offering some other maybe items that may be differentiating our pipeline, and that might be relaxed spec on the pipeline as well.

R
Robert Michael Kwan
Analyst

Okay, got it. Maybe if I can just finish, you had a comment on -- both in the MD&A and on the call on rail service and just working with the rail companies. Is that something where you're seeing issues right now, or potential issues brewing, or is that just a cautious statement given what we've seen for rail service, call it in the past year?

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

I would say it's a cautious statement. It's something that's not 100% within our control. So when we see situations like that, we try to mitigate our risk as much as possible. So we are working with the railroads again to try to make sure that we get the best service possible. I've been told that both lines have done a considerable -- made a considerable effort to staff up and add a lot more power and have made some investments since last year to again help improve their service.

R
Robert Michael Kwan
Analyst

And so far -- yes?

D
David G. Smith
President, CEO & Director

Robert, this is Dave here. I'll just chime in. I think Dean and his team have been working very hard through this year. I think it's fair to say that some of the challenges we had in the first quarter with the railways caught us a bit off guard. Since then, we've worked with the railways, but we've also established some contingency plans on our side so that, if we do see a degradation in service, we have some options to try and mitigate the effect of that. So I think at this stage -- I'm knocking on wood as I say this, but I think at this stage we're feeling a lot more confident going into this winter.

R
Robert Michael Kwan
Analyst

Got it. And I guess just to be clear, since -- in propane withdrawal, so far you haven't had any issues getting that product out?

C
C. Dean Setoguchi
Senior Vice President of Liquids Business Unit

Yes, that's correct. I think one thing that helps us with our propane egress is that we have 3 pipeline connected terminals that can export propane. That'd be at Rimbey, at our Edmonton terminal, and also our Josephburg terminal as well.

Operator

There are no further questions at this time. I will now return the call to our presenters.

L
Lavonne Zdunich
Director of Investor Relations & Communications

Thank you. At this point, that completes our third quarter call. If you have any further questions, please give either myself or Calvin Locke a call. Thank you for listening and have a good day.

Operator

This concludes today's conference call. You may now disconnect.